Our Latest Projects

we make alot of project with different industries

Changing conductors of 220 KV lines under live line

Client name: UMR Emeco/ON: 2010

Changing with INVAR for Pasos-West Cairo conductors of 220 KV lines under live line of 6 km -double circuit... Read More

Changing conductors of 220 KV lines under live line

Client name: ABB/ON: 2009

Installation of optical sibers with 375 km route length SABHA AREA... Read More

OPGW hot line stringing in different lines

Client Name: GRTE/ON 2005

Live line installation of OPGW cable including the splicing wotk ( 200 Km ) Read More

Toshka Substation 66KV

Client name: Egypt Electricty Company - Aswan Region /ON 2007

Studies, topgraphy, plans, civil engineering works and construction of transformer substation Toshka... Read More